On October 8, 2024, Ministry of Industry and Trade issued Official Letter No. 7940/BCT/DL requesting the People's Committees of provinces and centrally governed cities to implement several points related to the development of power projects, as regulated by Decree No. 115/2024/ND-CP. The goal is to ensure that power projects are implemented according to the approved timeline in the National Power Development Plan and the provincial electricity supply development plan.
09/02/2025
(i) For projects with investment approval requests submitted: Local authorities must review the legal status and actual conditions of the projects and urgently report to the competent authority for investment policy approval. This applies to both cases where there are multiple or only one interested investor.
(ii) For projects without investment approval requests submitted: A qualified consulting agency must be selected to prepare a pre-feasibility study report, which will serve as the basis for investor selection in accordance with investment and bidding regulations.
(iii) Regarding funding: The cost of preparing the pre-feasibility study report will follow the regulations of Decree No. 115/2024/NĐ-CP.
(iv) Guidance circular: The Ministry of Industry and Trade is in the process of drafting detailed guidance and expects to issue it in November 2024 to accelerate preparations and bidding processes for power projects.
The Official Letter calls for local governments to swiftly implement these measures.
--------------------------
For more information, please contact:
Hoang Pham (James) / Managing Partner at: hoang.pham@vselawyers.com
© 2023 VSE LAWYERS LIMITED LIABILITY LAW COMPANY – All rights reserved.
Attention: This legal update is not an advice and should not be treated as such.
If you would like to have any legal questions, please contact us for our advice