VIETUR CONSORTIUM HAS AWARDED BIDDER

On August 24, 2023, the Airports Corporation of Vietnam (#ACV) issued the Decision No. 3579/QĐ-TCTCHKVN, hereby decided to approve the Bidder selection results for Package No. 5.10, which pertains to the "Construction and Equipment Installation for the Passenger Terminal Building" of Component Project No. 3, under the broader Long Thanh International Airport Construction - Phase 1 project.

25/08/2023

VIETUR CONSORTIUM HAS AWARDED BIDDER

On August 24, 2023, the Airports Corporation of Vietnam (ACV) issued the Decision No. 3579/QĐ-TCTCHKVN, hereby decided to approve the Bidder selection results for Package No. 5.10, which pertains to the "Construction and Equipment Installation for the Passenger Terminal Building" of Component Project No. 3, under the broader Long Thanh International Airport Construction - Phase 1 project. Some highlights of the Decision is as below:

  1. The VIETUR consortium has won the contract for the construction and installation of the "Passenger Terminal Building" in Component Project No. 3 - Essential Facilities at the Long Thanh International Airport Phase 1 construction investment project.
  2. The winning bid amount is 27,813,939,171,360 VND and 338,849,894 USD, inclusive of value-added tax and other related fees.
  3. The contract execution period is 1,170 days, including weekends, holidays, and festivals as stipulated by the law.

Download the Decision here:

 https://drive.google.com/file/d/1xeBes3VAMly3e6E05L-kNicoZUDH3GdT/view?usp=sharing

----------

For more information, please contact:

Hoang Pham (James) / Managing Partner at: hoang.pham@vselawyers.com

© 2023 VSE LAWYERS LIMITED LIABILITY LAW COMPANY – All rights reserved.

Attention: This legal update is not an advice and should not be treated as such.

 


Subscribe To Legal Advice from VSE Lawyers

If you would like to have any legal questions, please contact us for our advice

0938 683 594