On June 17, 2023, the Energy Institute issued the Official Letter No.0975/VNL-P8 to report to the Ministry of Industry and Trade (the MOIT) about the development of the implementation plan of the PDP VIII in response to the Letter No. 3748/BCT-DL from the MOIT to the Energy Institute.
22/06/2023
On June 17, 2023, the Energy Institute issued the Official Letter No. 0975/VNL-P8 to report to the Ministry of Industry and Trade (the MOIT) about the development of the implementation plan of the PDP8 in response to the Letter No. 3748/BCT-DL from the MOIT to the Energy Institute.
On this Letter, the Energy Institute explained as below:
1. The Prime Minister only sets quantitative targets for the scale and structure of the national power generation and grid system for the final year of the planning period (2030) and the final year of the vision period (2050).
2. The PDP8 just includes a list of investment projects for the planning period and some related content.
3. Completing the planning tasks by June 2023 is impossible. Therefore, it is recommended that the MOIT allocate a reasonable timeframe for the Energy Institute to implement the planning tasks. Additionally, it is recommended to arrange funding to support the Institute in developing the planning tasks and reviewing the annual plan.
Below is the detailed Official Letter No. 0975/VNL-P8: